All Local, All The Time
The Boulder County Transportation Department announced the next round of closings for the 95th Street intersection improvement project.
Beginning at 8 a.m. on March 12, the following closures will be in effect:
The work being done includes completing the drainage, installing private utilities, and roadway widening/resurfacing. The same travel restrictions that were in place during the fall will be enforced during working hours, 8 a.m. to 4:30 p.m., Monday through Friday.
The department said that work and closures are expected to last through May.
Emergency services will have access through the construction zone at all times. Residents who live along the zone, their guests and their service providers will be granted access to the area at all times.
The project’s website is http://www.bouldercounty.org/transportation/plans-and-projects/95th-intersections. The site contains background information and provides updates as work progresses.
Reader Comments(0)